Press Release - 17th February 2012


Update on Moyle repair progress

 

Repairs have gone well since the last update. Earlier this week the second joint was completed and Pole 2 has been laid down on the sea bed and both water jet trenching and online testing have been successfully carried out. We now expect that the return to 450MW ATC will be at 0600 Sunday 19th February (ramp rate to remain at 5MW/minute until 0600 on 1st March).

 